Fill This Form To Receive Instant Help
Homework answers / question archive / 1) New Marketing Mailing Earned Value Analysis Your Name American InterContinental University Submission Date 2 Introduction Delete highlighted information
1) New Marketing Mailing Earned Value Analysis Your Name American InterContinental University Submission Date 2 Introduction Delete highlighted information. The introduction is the best opportunity to convince your audience that you have something worthwhile to say (one solid paragraph). An introduction can accomplish this by fulfilling five important responsibilities, as follows: 1. Get the audience's attention. 2. Introduce the topic. 3. Explain its relevance to the audience. 4. State a thesis or purpose. 5. Outline the main points. 3 Earned Value Analysis Scenario Jennifer and Ben turned in their status report for the newly approved mailing activities. Jennifer feels that they are on track with nothing for you to worry about. She reports the following information for the critical path tasks: You review her status report and determine that Jennifer does not have a solid grasp of the project status. Ben was unable to provide you with anything more than, "Things are moving along just fine." Conduct a Earned Value Analysis based on the following Template. Project Metrics Variances Cost Variance (CV) Complete the following tasks: 1. Discuss the CV metric, and include the equation (CV = EV – AC) and what the acronyms stand for. 2. Using the information below, use the formula to calculate the CV. Earned Value (EV) = $580 CV = Actual Costs (AC) is $600 4 3. Based on the CV that you calculated, explain the importance of the CV for the new marketing mailing scenario. 4. What happens when the EV is less than the AC? 5 Schedule Variance (SV) Complete the following tasks: 1. Discuss the SV metric, and include the equation (SV = EV – PV) and what the acronyms stand for. 2. Using the information below, use the formula to calculate the SV. Earned Value (EV) = $850 Planned Value = $1200 SV = 3. Based on the SV that you calculated, explain the importance of the SV for the new marketing mailing scenario. 4. What happens when the EV is less than the PV? 6 Performance Indices Cost Performance Index (CPI) 1. Discuss the CPI, and include the equation (CPI = EV/AC) and what the acronyms stand for. 2. Using the information below, use the formula to calculate the CPI. Earned Value (EV) = $580 Actual Costs (AC) is $600 CPI = 3. What does the CPI calculation mean? A CPI value of __________ indicates for every project dollar spent, only __________ in earned value. 4. How could the Albany Distribution Company increase the CPI? 7 Schedule Performance Index (SPI) Complete the following tasks: 1. Analyze the SPI, and include the equation (SPI = EV/PV) and what the acronyms stand for. 2. Using the information below, use the formula to calculate the SPI. Earned Value (EV) = $850 Planned Value (PV) = $1200 SPI = 3. What does the SPI calculation mean? A SPI value of __________ indicates for every dollar of work the project planned to accomplish at that point in time, $__________ worth of work was completed. 4. How could the Albany Distribution Company increase the SPI? 8 Earned Value Management (EVM) Methodology Complete the following tasks: 1. Explain the EVM methodology using a course resource. 2. Define two project metrics required to calculate earned value analysis (EVA). 3. How would you calculate the EVA? 4. What are the limitations of EVM? 9 Conclusion The conclusion is the last thing that the reader will remember about your essay. 1. The conclusion should be a summary of the highlights of your statement of purpose. 2. The conclusion should include the main points of the statement of purpose. 3. The conclusion should be as well-constructed and grammatically correct as everything. If you included the topics from Units 1–4 in your introduction, you must mention those in your conclusion. 10 References Example Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: A guide to measuring and monitoring project performance (3rd ed.). Wiley.
New Marketing Mailing Earned Value Analysis
Introduction
According to Ayn Rand, pride is the acknowledgement of the idea that people are their highest value and, like all of man’s values, it must be earned. The earned value analysis is a vital topic in project management, particularly in measuring a specific project’s success and progress in an objective way. For people wanting to measure their projects’ performance, this technique is excellent in helping them to make informed decisions. This paper looks at Jennifer and Ben’s case scenario to determine if the made the right steps. They turned their status report for a newly approved mailing activities. Jennifer feels that there is nothing to worry and they have done well in their tasks. However, this paper looks if Jennifer and Ben had sufficient control over this idea and if their assumptions on the project were right. As such, an earned value analysis (EVA) will be performed below.
Project Metrics
Variances
Cost Variance (CV)
Complete the following tasks:
CV = EV - AC
Where,
CV: Cost Variance
EV: Earned Value
AC: Actual Costs
Earned Value (EV) = $580, Actual Costs (AC) is $600
CV = $580 - $600 = - $20
As already discussed above, a CV is important because it helps an organization to track a project’s costs as it progresses. The calculated CV above is -$20, which has a negative value.
Schedule Variance (SV)
SV = EV - PV
Where,
SV: Schedule Variance
EV: Earned Value
PV: Planned Value
Earned Value (EV) = $850, Planned Value = $1200
SV = $850 - $1200 = - $350
The above SV helps in determining whether a project is ahead or behind the planned schedule. In this case, the SV has a negative value, which means that the project is far behind the planned schedule.
Performance Indices
Cost Performance Index (CPI)
CPI = EV/AC
Where,
CPI: Cost Performance Index
EV: Earned Value
AC: Actual Costs
Earned Value (EV) = $580, Actual Costs (AC) is $600
CPI = $580/$600 = 0.9667
A CPI value of 0.9667 indicates for every project dollar spent, only $0.9667 in earned value.
Schedule Performance Index (SPI)
SPI = EV/PV
Where,
SPI: Schedule Performance Indicator
EV: Earned Value
PV: Planned Value
Earned Value (EV) = $850, Planned Value (PV) = $1200
SPI = $850/$1200 = 0.7083
A SPI value of 0.7083 indicates for every dollar of work the project planned to accomplish at that point in time, $0.7083 worth of work was completed.
Earned Value Management (EVM) Methodology
This technique uses three vital elements, including cost, time, as well as scope. It, thus, compares the planned and actual values of a given project. Nevertheless, it avoids using accounting systems in finding actual costs. Hence, this methodology can be either done using individual names of project team members or by using generic categories.
Conclusion
As discussed above, this paper sought to determine whether Jennifer and Ben’s assessment of the given project offered a clear picture about its performance. However, the above analysis proves otherwise because the project has a negative SV.