Homework answers / question archive / San Jose State University BUS 140 Quiz 3 - Chap 3 TRUE/FALSE QUESTIONS 1)Crashing is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced
San Jose State University
BUS 140
TRUE/FALSE QUESTIONS
1)Crashing is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.