In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000

Accounting

In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows.

 

2021

2022

2023

Cost incurred during the year

$2,523,000

$3,177,000

$1,980,000

Estimated costs to complete as of year-end

6,177,000

1,800,000

0

Billings during the year

2,070,000

3,630,000

4,300,000

Cash collections during the year

1,835,000

3,400, 000

4,765,000

 

Westgate recognizes revenue over time according to percentage of completion.

Required:

1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.)

 

2021

2022

2023

Revenue

$2,523,000

 

 

Gross profit (loss)

$6,177,000

 

 

 