Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / Approach Company, which applies overhead to production on the basis of machine hours, reported the following data for the period just ended:   Actual units produced: 15,200 Actual fixed overhead incurred: $855,000 Standard fixed overhead rate: $13 per hour Budgeted fixed overhead: $820,000 Planned level of machine-hour activity: 62,000   If Approach estimates four hours to manufacture a completed unit, the company's fixed-overhead volume variance would be: Multiple Choice $15,600 negative

Approach Company, which applies overhead to production on the basis of machine hours, reported the following data for the period just ended:   Actual units produced: 15,200 Actual fixed overhead incurred: $855,000 Standard fixed overhead rate: $13 per hour Budgeted fixed overhead: $820,000 Planned level of machine-hour activity: 62,000   If Approach estimates four hours to manufacture a completed unit, the company's fixed-overhead volume variance would be: Multiple Choice $15,600 negative

Management

Approach Company, which applies overhead to production on the basis of machine hours, reported the following data for the period just ended:

 

Actual units produced: 15,200

Actual fixed overhead incurred: $855,000

Standard fixed overhead rate: $13 per hour

Budgeted fixed overhead: $820,000

Planned level of machine-hour activity: 62,000

 

If Approach estimates four hours to manufacture a completed unit, the company's fixed-overhead volume variance would be:

Multiple Choice

  • $15,600 negative.
  • $15,600 positive.
  • $35,000 negative.
  • $35,000 positive.
  • None of the answers is correct.

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Computation of Fixed-overhead Volume Variance:

Fixed Overhead Volume Variance = Standard Fixed Overhead for Actual Output - Budgeted Fixed Overhead

Here,

Standard Fixed Overhead for Actual Output= Actual Output * Estimated Number of Hour per Unit * Standard Fixed Overhead Rate

=15,200*4*13

=790,400

 

Budgeted Fixed Overhead = $820,000

 

Fixed overhead volume variance =$790,400-$820,000 = $29,600 Unfavorable

 

So, the correct option is 5th "None of the answers is correct".