Homework answers / question archive / 1  d out of Given the following information for the standard and special jobs during 2019: Standard Special Cost Driver Total costs Number of jobs 400 200 machine hour per job 10 10 setup hours per job 4 7 Machine operations machine hour $150,000 Setups setup hours $ 90,000 Purchase orders 400 500 # of purchases $ 36,000 Using ABC costing, allocated setup cost for each standard job will be ---- 2  Given the following information for the standard and special jobs during 2019: Standard Special Driver Total costs Number of jobs 450 250 machine hour per job 10 10 setup hours per job 7 Machine operations machine hour $150,000 Setups setup hours $ 90,000 Purchase orders 500 500 # of purchases $ 36,000 4 Using ABC costing, overhead cost of each standard job will be A- 1 B ili III OP

1  d out of Given the following information for the standard and special jobs during 2019: Standard Special Cost Driver Total costs Number of jobs 400 200 machine hour per job 10 10 setup hours per job 4 7 Machine operations machine hour $150,000 Setups setup hours $ 90,000 Purchase orders 400 500 # of purchases $ 36,000 Using ABC costing, allocated setup cost for each standard job will be ---- 2  Given the following information for the standard and special jobs during 2019: Standard Special Driver Total costs Number of jobs 450 250 machine hour per job 10 10 setup hours per job 7 Machine operations machine hour $150,000 Setups setup hours $ 90,000 Purchase orders 500 500 # of purchases $ 36,000 4 Using ABC costing, overhead cost of each standard job will be A- 1 B ili III OP

Accounting

d out of Given the following information for the standard and special jobs during 2019: Standard Special Cost Driver Total costs Number of jobs 400 200 machine hour per job 10 10 setup hours per job 4 7 Machine operations machine hour $150,000 Setups setup hours $ 90,000 Purchase orders 400 500 # of purchases $ 36,000 Using ABC costing, allocated setup cost for each standard job will be ----

Given the following information for the standard and special jobs during 2019: Standard Special Driver Total costs Number of jobs 450 250 machine hour per job 10 10 setup hours per job 7 Machine operations machine hour $150,000 Setups setup hours $ 90,000 Purchase orders 500 500 # of purchases $ 36,000 4 Using ABC costing, overhead cost of each standard job will be A- 1 B ili III OP

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Particulars Standard Special Total Cost Cost per cost driver Standard Special
  A B C = A + B D E = D / C A X E B X E
Machine hours        4,000        2,000        6,000 $ 150,000 $ 25.00 100,000            50,000
Setup Hours        1,600        1,400        3,000 $ 90,000 $ 30.00      48,000            42,000
Purchase orders           400           500           900 $ 36,000 $ 40.00      16,000            20,000

Allocated setup cost for each standard job = 48,000 / 400 = $120 per job ($30 X 4 hours)

Answer:

  Standard Special
  Rate Usage Allocation Usage Allocation
Machine operation cost $         21.43 4500 $      96,429 2500 $      53,571
Setups Cost $         25.35 1800 $      45,634 1750 $      44,366
Purchase orders cost $         36.00 500 $      18,000 500 $      18,000
Total overhead cost $   160,062   $    115,938
Number of jobs               450                  250
Overhead cost per job $     355.69   $      463.75

Working:

Activity Cost Pool Overhead Costs Total cost drivers Activity Rate
Machine operation cost $            150,000                        7,000 $        21.43 per machine hour
Setups Cost $              90,000                        3,550 $        25.35 per setup
Purchase orders cost $              36,000                        1,000 $        36.00 per order
Calculation of usage:    
Job Type Standard Special Total
Number of jobs 450 250  
Machine hour per job 10 10  
Total machine hours 4500 2500       7,000
Set up hours per job 4 7  
Total set up hours 1800 1750       3,550
Purchase orders 500 500       1,000