Fill This Form To Receive Instant Help
Homework answers / question archive / Strayer University BUS 430 TRUE/FALSE 1)Because the preparation of annual reports is done on a repeating basis, project management techniques are not appropriate
|
Complete the following table.
Activity |
Time |
Earliest Start |
Earliest Finish |
Latest Start |
Latest Finish |
Slack |
On Critical Path? |
A |
|
|
|
|
|
|
|
B |
|
|
|
|
|
|
|
C |
|
|
|
|
|
|
|
D |
|
|
|
|
|
|
|
E |
|
|
|
|
|
|
|
F |
|
|
|
|
|
|
|
G |
|
|
|
|
|
|
|
H |
|
|
|
|
|
|
|
Complete the following table:
Activity |
Time |
Earliest Start |
Earliest Finish |
Latest Start |
Latest Finish |
Slack |
On Critical Path? |
A |
|
|
|
|
|
|
|
B |
|
|
|
|
|
|
|
C |
|
|
|
|
|
|
|
D |
|
|
|
|
|
|
|
E |
|
|
|
|
|
|
|
F |
|
|
|
|
|
|
|
Activity |
Slack |
Normal Time |
Crash Time |
Normal Cost |
Crash Cost |
Crash Cost Per Week |
A |
0 |
7 |
4 |
$ 400 |
$ 750 |
|
B |
1 |
12 |
9 |
$ 1,000 |
$2,200 |
|
C |
0 |
7 |
6 |
$ 800 |
$1,100 |
|
D |
0 |
6 |
5 |
$ 600 |
$1,000 |
|
E |
0 |
8 |
6 |
$ 1,200 |
$2,200 |
|
F |
9 |
3 |
2 |
$ 800 |
$1,000 |
|
G |
9 |
3 |
2 |
$ 500 |
$ 650 |
|
H |
0 |
4 |
3 |
$ 400 |
$ 600 |
|
I |
0 |
6 |
5 |
$ 900 |
$1,300 |
|
|
Activity |
Normal Time (Months) |
Crash Time (Months) |
Normal Cost |
Crash Cost |
Crash Cost/Month |
A |
3 |
2 |
$100,000 |
$150,000 |
|
B |
6 |
4 |
$200,000 |
$320,000 |
|
C |
2 |
2 |
$ 90,000 |
$ 90,000 |
|
D |
2 |
1 |
$180,000 |
$250,000 |
|
E |
4 |
2 |
$225,000 |
$450,000 |
|
F |
7 |
6 |
$ 80,000 |
$120,000 |
|
G |
4 |
2 |
$310,000 |
$500,000 |
|
H |
2 |
2 |
$400,000 |
$400,000 |
|
Activity |
Optimistic Time |
Most Likely Time |
Pessimistic Time |
A |
7 |
9 |
14 |
B |
2 |
2 |
8 |
C |
8 |
12 |
16 |
D |
3 |
5 |
10 |
E |
4 |
6 |
8 |
F |
6 |
8 |
10 |
G |
2 |
3 |
4 |
H |
2 |
2 |
8 |
I |
6 |
8 |
16 |
J |
4 |
6 |
14 |
K |
2 |
2 |
5 |
Activity |
Immediate Predecessors |
Normal Time (weeks) |
a. order materials |
none |
4 |
b. clear job sites |
none |
6 |
c. excavate job sites |
b |
10 |
d. make trenches for conduit |
b |
6 |
e. install conduit |
d |
10 |
f. form and pour foundations |
c, d |
8 |
g. install wire |
f |
6 |
h. install lighting standards |
g |
5 |
i. install luminaries |
h |
4 |
j. connect to service |
i |
3 |
Activity |
Immediate Predecessors |
Normal Time (days) |
a. organize layout team |
none |
5 |
b. organize modification team |
none |
3 |
c. design personnel jobs |
a |
2 |
d. set machinery in place |
b |
3 |
e. connect utilities |
c, d |
7 |
f. modify conveyor system |
e |
4 |
g. train personnel |
e |
3 |
h. finishing touches |
f |
5 |
i. run test lot |
g |
2 |
Activity |
Immediate Predecessors |
Optimistic to |
Most Likely tm |
Pessimistic tp |
a |
none |
8 |
10 |
12 |
b |
none |
6 |
7 |
9 |
c |
b |
3 |
3 |
3 |
d |
a |
10 |
15 |
20 |
e |
d |
6 |
7 |
8 |
f |
c |
9 |
10 |
11 |
g |
d |
5 |
7 |
10 |
h |
e,f |
14 |
15 |
16 |
Activity |
Immediate Predecessors |
Optimistic to |
Most Likely tm |
Pessimistic tp |
a |
none |
4 |
6 |
7 |
b |
a |
1 |
2 |
3 |
c |
a |
5 |
5 |
5 |
d |
b |
7 |
9 |
12 |
e |
b |
2 |
4 |
8 |
f |
c,d |
6 |
9 |
10 |
Activity |
Optimistic to |
Most Likely tm |
Pessimistic tp |
b |
15 |
17 |
20 |
d |
21 |
22 |
22 |
e |
27 |
30 |
35 |
g |
23 |
27 |
29 |
i |
25 |
31 |
34 |
Path |
te |
Vt |
1 |
27 |
2.32 |
2 |
25 |
4.12 |
3 |
29 |
1.89 |
Immediate |
Present |
Accelerated |
|||
Activity |
Predecessors |
Duration |
Cost |
Duration |
Cost |
a |
none |
3 |
$100 |
2 |
$250 |
b |
a |
4 |
$ 50 |
3.5 |
$150 |
c |
a |
5 |
$250 |
4 |
$450 |
d |
none |
3 |
$100 |
3 |
--- |
e |
d |
6 |
$100 |
5 |
$175 |
f |
b,c,e |
7 |
$300 |
5 |
$600 |
|
Immediate |
Present |
Accelerated |
||
Activity |
Predecessors |
Duration |
Cost |
Duration |
Cost |
a |
none |
3 |
3300 |
2 |
3400 |
b |
none |
5 |
4100 |
3 |
4500 |
c |
a |
4 |
3700 |
3 |
3800 |
d |
b |
5 |
5900 |
4 |
6000 |
e |
c |
6 |
6700 |
4 |
6900 |
f |
c |
4 |
4100 |
3 |
4150 |
g |
d,e |
6 |
9100 |
3 |
9700 |
h |
f,g |
5 |
2700 |
4 |
3000 |
Activity A |
Immediate Predecessor(s) none |
Activity Time (weeks) 1 |
B |
A |
2 |
C |
A |
3 |
D |
A, B |
4 |
E |
C, D |
3 |
F |
D, E |
2 |
Project Activity |
Immediate Predecessor(s) |
Optimistic Time |
Most Likely Time |
Pessimistic Time |
Expected Time |
Activity Variance |
A |
none |
2 |
5 |
14 |
6 |
4 |
B |
none |
8 |
11 |
14 |
11 |
1 |
C |
A |
5 |
7 |
9 |
7 |
0.44 |
D |
A |
6 |
9 |
12 |
9 |
1 |
E |
B, C, D |
1 |
3 |
5 |
3 |
0.44 |
please use this google drive link to download the answer file.
https://drive.google.com/file/d/1BiaBRAjeVs9GZDLrR05ygdaL7Xq2CtKC/view?usp=sharing
note: if you have any trouble in viewing/downloading the answer from the given link, please use this below guide to understand the whole process.
https://helpinhomework.org/blog/how-to-obtain-answer-through-google-drive-link