Homework answers / question archive / Assume Project A has a present value of net cash inflows of $79,600 and an initial investment of $60,000
Assume Project A has a present value of net cash inflows of $79,600 and an initial investment of $60,000. Project B has a present value of net cash inflows of $82,500 and an initial investment of $75,000. Assuming the projects are mutually exclusive, which project should management select? Justify your answer through work out.
Computation of Net Present Value:
Net Present Value = - Initial Investment + Net Present Value of Cash Inflows
For Project A:
Net Present Value = -$60,000 + $79,600 = $19,600
For Project A:
Net Present Value = -$75,000 + $82,500 = $7,500
Project A should be accepted as Net Present Value is higher for Project A.