1) An electric power plant uses solid waste for fuel in the production of electricity. The cost Y in dollars per hour to produce electricity is Y = 12 + 0.4X + 0.18X^2, where X is in megawatts. Revenue in dollars per hour from the sale of electricity is 16X - 0.2X^2. Find the value of X that gives maximum profit. The value of X that gives maximum profit is megawatts. (Round to two decimal places.)

2) An electric power plant uses solid waste for fuel in the production of electricity. The cost Y in dollars per hour to produce electricity is Y = 12+ .3x+.27x2, where x is in megawatts. Revenue in dollars per hour from the sale of electricity is 15x-.2x2. Find the value of X that gives maximum profit.

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Answer:

2) profit= revenue-cost
=15x-.2x2-12- .3x-.27x2

= 14.7x-.47x2-12

for profit to be maximum differenciate

14.7-.94x=0

x=15.64MW

1) 

please use this google drive link to download the answer file.

https://drive.google.com/file/d/1AoPUS35l5puduaK0Pzg2uLkkJz92b9oz/view?usp=sharing

note: if you have any trouble in viewing/downloading the answer from the given link, please use this below guide to understand the whole process.

https://helpinhomework.org/blog/how-to-obtain-answer-through-google-drive-link