enter at the rate of 6 units per minute. All units wait in line for Step A and then do Step A. Then about 40% go to wait in line for step B. When flow units finish Step B, 40% exit. The remaining 60% go to Step C. About 50% of the units leaving Step A go to Step C. So, Step C has two flows into it (from B and from A) The remaining units leaving step A 10% go to Step D. After Step C, 80% of the flow units that went through Step C exit. The rest go to Step D. All flow units going to Step D exit after Step D. So there are 2 flows into Step D (Step A, Step C) On average 2 units are waiting for Step A and it takes 3 minutes to do Step A. On average 1 units are waiting for Step B and it takes 10 minutes to do Step B On average 3 units are waiting for Step C and it takes 3 minutes to do Step C On average 1 units are waiting for Step D and it takes 6 minutes to do Step D