Homework answers / question archive / In a resource-constrained project the second priority in assigning resources is usually given to activities with the     Most slack

In a resource-constrained project the second priority in assigning resources is usually given to activities with the     Most slack

Business

In a resource-constrained project the second priority in assigning resources is usually given to activities with the

   

Most slack.

   

Least slack.

   

Highest cost.

   

Lowest identification number.

   

Smallest duration.