Transmissions are delivered to the fabrication line four at a time. It takes one hour for transmissions to be delivered. Approximately four vehicles are produced each hour, and management has decided that 50 percent of expected demand should be maintained as safety stock. How many kanban card sets are needed?

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Answer:

D = 4 per hour

T = 1 hour

C = 4 at a time

X = 50% or 0.5

Number of Kanban = 4*1*(1+0.5)/4 = 1.5

Thus, 2 Kanban sets will be required