Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / Q2: Dawson Toys, Ltd

Q2: Dawson Toys, Ltd

Accounting

Q2: Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.50 per micron Direct labor: 1.3 hours per toy at $8 per hour During July, the company produced 3,000 Maze toys. Production data for the month on the toy follow: Direct materials: 25,000 microns were purchased at a cost of $0.48 per micron. 5,000 of these microns were still in inventory at the end of the month. Direct labor: 4.000 direct labor-hours were worked at a cost of $36,000. Required: 1. Compute the following variances for July: a. Direct materials price and quantity variances. b. Direct labor rate and efficiency variances. 2. Prepare a brief explanation of the possible causes of each variance.

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Answer :-

a)

Standard Quantity (SQ)

3000*6

$18,000

Standard Price (SP)

 

1.30

Actual Quantity(AQ)

25,000-5,000

20,000

Actual Price(AP)

 

0.48

Direct material price variance :-

Material Price Variance = AQ *(SP - AP)

Material Price Variance = 25,000*(0.50- 0.48)

Material Price Variance = $500

Material Price Variance = $500 F

  Direct material Quqntity variance :-

Material Quantity Variance = SP* (SQ - AQ)

Material Quantity Variance = 0.50* (18,000- 20,000)

Material Quantity Variance = -1,000

Material Quantity Variance = 1,000 U

b)

Actual hours

36,000/4,000

$9.00

Standard hours

1.30*3000

3,900 hrs

Direct labor rate variance :-

Direct labor rate variance = (std.rate - actual rate )*Actual hrs

Direct labor rate variance  = ($8.00-$9.00)*4,000

Direct labor rate variance  = - $4,000
Direct labor rate variance  = $ 4,000 Unfavourable

Direct labor Efficiency variance :-

Direct labor Efficiency variance = (std.hrs - actual hrs )*Std.rate

Direct labor Efficiency variance   = (3,900-4,000)*8

Direct labor Efficiency variance   = - $800
Direct labor Efficiency variance   = $ 800 Unfavourable

2)

2.

Variances arise when there is different between the standard (the planned cost) and the cost which has actually incurred. Standard cost means cost that should have been incurred whereas actual cost means cost that has actually been incurred and any difference between the both leads to variance.

Explanation

Variance arises when there is a difference between the standard cost and the actual cost. Based on the type of variance, it can either be favorable or unfavorable.

In the given case, the following variances have been computed:

Direct material price variance: The standard price ($0.50) per unit is more than the actual price of $0.48 and this means that the business has saved $0.02 on per unit of the materials purchased. Thus, there exists a favorable variance of $500 ($0.02 per unit × 25,000 microns).

Direct material quantity variance: The standard quantity of material that should be used to produce 3000 toys (that is 18,000 microns) is less than the actual microns used (that is, 20,000). Since the standard quantity that should have been used is less than the actual quantity used, there exists an unfavorable variance of $1,000.

Direct labor rate variance: The standard rate ($8) per hour that should have been paid to the laborers is lower than the rate at which the laborers were actually paid for the actual number of hours worked. Since the standard rate is lower than the actual rate per hour, there exists an unfavorable variance of $4,000.

Direct labor efficiency variance: The standard hours (3,900 hours) to produce the 3,000 toys are lower than the actual hours. This means that the labors have actually taken more than the number of hours that should have been taken to complete those toys. Thus, there exists an unfavorable variance of $800.