Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / 1  Product A Product B Total costs $ Given the following information: Activity Cost driver Machining machine hours Setup Production runs Inspection Inspection hours Number of units 20,000 hr 50,000 hr $375,000 50 runs 60 runs $120,000 1000 hr 500 hr $105,000 50,000 100,000 Using activity based costing, the allocated manufacturing overhead cost per unit of product Bis- A- B I EE OP 2  A manufacturing process is used to produce masses of identical units

1  Product A Product B Total costs $ Given the following information: Activity Cost driver Machining machine hours Setup Production runs Inspection Inspection hours Number of units 20,000 hr 50,000 hr $375,000 50 runs 60 runs $120,000 1000 hr 500 hr $105,000 50,000 100,000 Using activity based costing, the allocated manufacturing overhead cost per unit of product Bis- A- B I EE OP 2  A manufacturing process is used to produce masses of identical units

Accounting

Product A Product B Total costs $ Given the following information: Activity Cost driver Machining machine hours Setup Production runs Inspection Inspection hours Number of units 20,000 hr 50,000 hr $375,000 50 runs 60 runs $120,000 1000 hr 500 hr $105,000 50,000 100,000 Using activity based costing, the allocated manufacturing overhead cost per unit of product Bis- A- B I EE OP

A manufacturing process is used to produce masses of identical units. Given the following: Physical WIP beginning (90 % Direct material, 60 X conversion) 500 units Started during current period 9,500 units WIP Ending (80 % Direct material, 40% conversion) 1,000 units Using FIFO method, the work done to date in current period in equivalent unit for conversion costs will be 1 ?" B I c?

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Allocated machining cost ($375,000/(20,000+50,000)*50,000) $ 267,857.14
Allocated setup cost ($120,000/(50+60)*60) $    65,454.55
Allocated inspection cost ($105,000/(1,000+500)*500) $    35,000.00
Total allocated overhead $ 368,311.69
Number of units produced            100,000
Manufacturing overhead cost per unit ($368,311.69/100,000)

$     3.683117

Equivalent Unit under FIFo System

  Physical % of current period Equivalent unit of conversion
Beginning WIP 500 40% 200
Units started and completed (9500-1000) 8500 100% 8500
Ending WIP 1000 40% 400
Total     9100