Yani Company purchased land for $115,000 with the intentions of constructing a new operating facility
Yani Company purchased land for $115,000 with the intentions of constructing a new operating facility. The land purchase included a dilapidated building that was removed at a cost of $16,000. The only salvage value from this old building was some materials which were sold for proceeds of $4,000. Yani had paid surveying costs of $1,800 and legal fees related to land transfer of $6,700. The new building was quickly constructed at a total cost of $422,000. Permits on the construction of this new facility totalled $18,000. Insurance premiums of $9,200 are paid annually. The production manager is currently on-site facilitating the production startup. This manager is an annual salary of $85,000. What capital cost is assigned to the land?
Expert Solution
Computation of Total Capital Cost of Building:
Total Capital Cost of Building = Cost of Construction + Permit Fees for Construction
= $422,000+$18,000
Total Capital Cost of Building = $440,000.