ABC & Associates is a public accounting firm that specialises in providing accounting and auditing service. Its job-costing system has one direct cost pool, professional labour and a single indirect cost pool that includes all supporting costs of running the office. The support costs are allocated to clients on the basis of professional labour-hours. In addition to the two senior partners, ABC has six partners who work directly with clients. Each of the eight partners is expected to work for approximately 2 650 hours a year. Budgeted and actual costs for 2016 were: Budgeted professional labour costs $4 240 000 Budgeted support costs $2 000 000 Actual professional labour costs $4 893 000 Actual support costs $2 400 000 Actual total professional hours 23 300 hours Required: Calculate the indirect costs rate per professional labour-hour under: (a) Actual costing (b) Normal costing (10 marks) (10 marks)

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Answer:-

(a) Actual costing

Under Actual costing method, all the actual amount incurred i.e actual labour cost, actual material cost and actual overhead incurred would be considered.

Indirect costs are those costs incurred by the entity which is not directly related to production or any service. we cannot compare the indirect cost vis a vis production. These costs incurred in supportive in nature to facilitate the production or service.

Indirect cost per professional labour hour is as follows :- (Under Actual cost method)

Indirect Cost per professional labour hour = Actual support cost / Actual total professional hours

= $ 2,400,000 / 23,300

=$ 103

(b) Normal Costing

Under Normal costing, predetermeined over head rate is estimated and same can be used to assigh the overhead to products or services. In other words, the overhead rate under normal costing is based on the expected overhead cost and expected machine hours or man hours or other suitable cost driver.

In the given case, we need to calculate the expected professional labour hours

Expected Professional labour hours = 8 Partners x 2, 650 hours

= 21,200 hours

Budgeted support costs = $ 2,000,000

Indirect cost per professional labour hour is as follows :- (Under Normal cost method)

Indirect Cost per professional labour hour = Budgeted support cost / Expected total professional hours

= $ 2,000,000/ 21,200

= $ 94.34.