Ch.3 MULTIPLE CHOICE

1)Which of the following statements about Bechtel is true?

 

  1. The phases of project management are

 

  1. Which of the following statements regarding project management is false?

 

  1. A code of ethics especially for project managers

 

  1. Divulging information to some bidders on a project to give them an unfair advantage

 

 

  1. Which of the following statements regarding Gantt charts is true?

 

  1. Which of the following statements regarding critical paths is true?

 

  1. Which of the following statements regarding CPM is true?

 

  1. A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8.

 

  1. A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of

F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8.

 

  1. A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E.

 

 

  1. Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is true?

 

 

  1. Which of the following statements regarding CPM networks is true?

 

  1. Activity M on a CPM network has predecessors N and R, and has successor S. M has duration 5. N's late finish is 18, while R's is 20. S's late start is 14. Which of the following is true?

 

  1. Which of the following statements concerning CPM activities is false?

 

  1. The time an activity will take assuming very unfavorable conditions is

 

 

  1. The          distribution is used by PERT analysis to calculate expected activity times and variances.

 

  1. The expected activity time in PERT analysis is calculated as

 

  1. Which of the following statements regarding PERT times is true?

 

  1. Which of the following statements regarding PERT times is true?

 

  1. The Beta distribution is used in project management to

 

 

  1. The Beta distribution is used in project management to

 

  1. In a PERT network, non-critical activities that have little slack need to be monitored closely

 

  1. Which of the following statements regarding PERT analysis is true?

 

 

  1. A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, the probability that the project will take 224 days or more to complete is

 

  1. An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is

 

  1. An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is

 

 

  1. An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 8. Its expected time and variance (if it is a critical activity) are

 

 

  1. A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, the probability

 

that the project will be completed in 95 days or less is

 

  1. A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, the probability that the project will be completed in 88 days or less is

 

 

  1. A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. The probability that the project can be completed between days 108 and 120 is

 

  1. A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days. The sum of all activity variances is 81; the sum of variances along the critical path is 64. The probability that the project will take 130 or more days to complete is

 

  1. Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day                        .

 

  1. A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before day                                                                                          (rounded to nearest day).

 

 

  1. A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before day                                                                                          (rounded to nearest day).

 

  1. Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline?

 

  1. Which of these statements regarding time-cost tradeoffs in CPM networks is true?

 

  1. What was the name of the construction project to rebuild the Pentagon after the terrorist attacks on Sept. 11, 2001?

 

  1. Which of the following statements regarding time-cost tradeoffs in CPM networks is false?

 

  1. If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of

$1,500, the crash cost per period is

 

  1. Two activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity             should be crashed first, adding

             to project cost.

Activity Normal Time Normal Cost Crash Duration Crash Cost One 8 days $6,000 6 days $6,800

Two 10 days $4,000 9 days $5,000

 

  1. If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of

 

$2,000, the crash cost per period is

 

  1. A network has been crashed to the point where all activities are critical. Additional crashing

 

 

Option 1

Low Cost Option
Download this past answer in few clicks

4.83 USD

PURCHASE SOLUTION

Already member?


Option 2

Custom new solution created by our subject matter experts

GET A QUOTE

Related Questions