 Vienna Chocolate Company produces fudge in large batches

Accounting Mar 30, 2021

 Vienna Chocolate Company produces fudge in large batches. One batch of fudge has the following standard costs and amounts: 

Standard kilograms of sugar

100

Standard cost per kilogram of sugar

$1.90

Standard direct labour hours

2.0

Standard direct labour cost per hour

$18.00

Vienna Chocolate Company produced 400 batches of fudge in the most recent month. Actual input costs and per batch usage levels were as follows:

Actual kilograms of sugar used

102

Actual cost per kilogram of sugar

$2.10

Actual direct labour hours

1.8

Actual direct labour cost per hour

$17.50

 

Required:

a) Calculate the total material input rate variance.

b) Calculate the total material efficiency variance.

c) Calculate the total labour rate variance.

d) Calculate the total labour efficiency variance.

Expert Solution

a) Computation of the total material input rate variance:-

Actual quantity = 400 * 102

= 40,800

Material input rate variance = (Actual cost - Standard cost) * Actual quantity

= ($2.10 - $1.90) * 40,800

= $0.20 * 40,800

= $8,160 (U)

 

b) Computation of the total material efficiency variance:-

Standard quantity = 400 * 100

= 40,000

Material efficiency variance = (Actual quantity - Standard Quantity) * Standard cost

= (40,800 - 40,000) * $1.90

= 800 * $1.90

= $1,520 (U)

 

c) Computation of the total labor rate variance:-

Actual direct labor hours = 1.80 * 400

= 720 hours

Labor rate variance = (Actual rate - Standard rate) * Actual direct labor hours

= ($17.50 - $18.00) * 720

= $0.50 * 720

= $360 (F)

 

d) Computation of the total labor efficiency variance:-

Standard direct labor hours = 400 * 2.00

= 800

Labor efficiency Variance = (Actual labor hours - Standard labor hour) * Standard Rate

= (720 - 800) * $18.00

= 80 * $18.00

= $1,440 (F)

Archived Solution
Unlocked Solution

You have full access to this solution. To save a copy with all formatting and attachments, use the button below.

Already a member? Sign In
Important Note: This solution is from our archive and has been purchased by others. Submitting it as-is may trigger plagiarism detection. Use it for reference only.

For ready-to-submit work, please order a fresh solution below.

Or get 100% fresh solution
Get Custom Quote
Secure Payment