Which of the following statements is not correct about Scientific Risk Management Process? Select one: O a

Finance

Which of the following statements is not correct about Scientific Risk Management Process? Select one: O a. Risk control is followed by risk monitoring b. Risk avoidance comes before risk measurement O c. Risk measurement comes after risk identification O d. Risk identification is the first step

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Correct Ans is "B. Risk Avoidance comes after risk measurement"

Risk Management Process involves following steps -

a) Risk identification

b) Risk analyzing

c) Risk evaluation / Measurement

d) Risk monitoring

e) Risk control / Avoidance