Scott has just been given a project that has a specific completion date. After a discussion with top management he finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The completion date is best classified as
Reduced. |
||
Constrained. |
||
Optional. |
||
Limited. |
||
Accepted. |