Homework answers / question archive / There are 5 steps involved when defining a project; which of the following is the last?     Develop the responsibility matrix     Code the WBS for tracking     Assign the cost account to a manager     Assign the work package to a manager     All of these are included in the final step

There are 5 steps involved when defining a project; which of the following is the last?     Develop the responsibility matrix     Code the WBS for tracking     Assign the cost account to a manager     Assign the work package to a manager     All of these are included in the final step

Business

There are 5 steps involved when defining a project; which of the following is the last?

   

Develop the responsibility matrix

   

Code the WBS for tracking

   

Assign the cost account to a manager

   

Assign the work package to a manager

   

All of these are included in the final step.