Homework answers / question archive / There are 5 steps involved when defining a project; which of the following is the last? Develop the responsibility matrix Code the WBS for tracking Assign the cost account to a manager Assign the work package to a manager All of these are included in the final step
There are 5 steps involved when defining a project; which of the following is the last?
Develop the responsibility matrix |
||
Code the WBS for tracking |
||
Assign the cost account to a manager |
||
Assign the work package to a manager |
||
All of these are included in the final step. |