Homework answers / question archive / The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A                    ? 6 B                    A 3 C                    A 7 D                    C 2 E                    B, D 4 F                    D 3 G                    E, F 7   b

The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A                    ? 6 B                    A 3 C                    A 7 D                    C 2 E                    B, D 4 F                    D 3 G                    E, F 7   b

Operations Management

The following activities are part of a project to be scheduled using CPM:

ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A                    ? 6
B                    A 3
C                    A 7
D                    C 2
E                    B, D 4
F                    D 3
G                    E, F 7
 
b. What is the critical path?
   
 
  A-B-E-G
  A-C-D-E-G
  A-C-D-F-G
  C-D-F-G
c. How many weeks will it take to complete the project?
  Number of weeks  
d. How much slack does activity B have?
  Slack of activity B weeks

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

please use this google drive link to download the answer file.

https://drive.google.com/file/d/1dhh0GGdLHc-g-63dyNzZlK8eG-ul9Ddp/view?usp=sharing

note: if you have any trouble in viewing/downloading the answer from the given link, please use this below guide to understand the whole process

https://helpinhomework.org/blog/how-to-obtain-answer-through-googledrive-link