The following activities are part of a project to be scheduled using CPM:
ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
A | ? | 6 |
B | A | 3 |
C | A | 7 |
D | C | 2 |
E | B, D | 4 |
F | D | 3 |
G | E, F | 7 |
b. | What is the critical path? | ||||||||
|
c. | How many weeks will it take to complete the project? |
Number of weeks |
d. | How much slack does activity B have? |
Slack of activity B | weeks |
please use this google drive link to download the answer file.
https://drive.google.com/file/d/1dhh0GGdLHc-g-63dyNzZlK8eG-ul9Ddp/view?usp=sharing
note: if you have any trouble in viewing/downloading the answer from the given link, please use this below guide to understand the whole process
https://helpinhomework.org/blog/how-to-obtain-answer-through-googledrive-link