Homework answers / question archive / The centerline of a c control chart is determined to be 16
on these information, an observed c of 25 indicates
a.The process is in control because the observed c is greater than the lower control limit of 4
b.The process is in control because the observed c is smaller than the upper control limit of 28
c.The process is in control because the observed c is between the lower control limit of 4 and the upper control limit of 28
d.Not enough information given to answer this question