Homework answers / question archive / Splitting an activity can result in all of the following EXCEPT A resource being moved from one activity to another and then back
Splitting an activity can result in all of the following EXCEPT
A resource being moved from one activity to another and then back. |
||
Possible startup and shutdown costs. |
||
A better project schedule. |
||
Activity work being placed on hold for a period until more resources are available. |
||
More people working on the same activity. |