Use the net present value technique to evaluate the following two projects and advice management on which one to choose. Use a discount rate of 13.5%.
YEAR |
PROJECT A |
PROJECT B |
0 |
(120,000) |
(120,000) |
1 |
30,500 |
51,000 |
2 |
32,500 |
45,000 |
3 |
64,500 |
12,600 |
4 |
39,471 |
17,000 |
Your PVIF should be approximated to 4 decimal places.