Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / When the present value of the cash inflows exceeds the initial cost of a project, then the project should be Group of answer choices: Rejected because the internal rate of return is negative Accepted because NPV > 0 Accepted because the profitability index is less than 1

When the present value of the cash inflows exceeds the initial cost of a project, then the project should be Group of answer choices: Rejected because the internal rate of return is negative Accepted because NPV > 0 Accepted because the profitability index is less than 1

Finance

When the present value of the cash inflows exceeds the initial cost of a project, then the project should be

Group of answer choices:

Rejected because the internal rate of return is negative

Accepted because NPV > 0

Accepted because the profitability index is less than 1.

Rejected because NPV>IRR

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Option b is correct

NPV is calculated as the present value of cash inflows minus the initial cost.

If present value of cash inflows exceeds initial cost, then the NPV is higher than zero and should be accepted