Fill This Form To Receive Instant Help
Homework answers / question archive / When Job 117 was completed, direct materials totaled $33,113; direct labor, $47,462; and factory overhead, $29,801
When Job 117 was completed, direct materials totaled $33,113; direct labor, $47,462; and factory overhead, $29,801. A total of 3,066 units were produced at a per-unit cost of Oa. $110,376 Ob. $80,575 Oc. $3,066 Od. $36
Answer is Option D
Explanation :
JOB COST SHEET 117 | |
Direct mterial | $ 33,113 |
Direct labor | $ 47,492 |
Factory Overhead | $ 29,801 |
Total Manufacturing cost | $ 110,406 |
Unit product Cost = Total Manufacturing cost / Total Number of Units
= $ 110,406 / 3,066
Unit product Cost = $ 36