Homework answers / question archive / Scenario Analysis Shao Industries is considering a proposed project for its capital budget

Scenario Analysis Shao Industries is considering a proposed project for its capital budget

Finance

Scenario Analysis

Shao Industries is considering a proposed project for its capital budget. The company estimates the project's NPV is $12 million. This estimate assumes that the economy and market conditions will be average over the next few years. The company's CFO, however, forecasts there is only a 50% chance that the economy will be average. Recognizing this uncertainty, she has also performed the following scenario analysis:

Economic
Scenario
Probability of
Outcome

NPV
Recession 0.05 -$38 million    
Below average 0.20 -26 million    
Average 0.50 12 million    
Above average 0.20 24 million    
Boom 0.05 38 million    

What is the project's expected NPV, its standard deviation, and its coefficient of variation? Enter your answers for the NPV and standard deviation in millions. For example, an answer of $1.2 million should be entered as 1.2, not 1,200,000. Round your answers to two decimal places.

E(NPV) $   million
σNPV $   million
CVNPV     

Option 1

Low Cost Option
Download this past answer in few clicks

2.86 USD

PURCHASE SOLUTION

Already member?


Option 2

Custom new solution created by our subject matter experts

GET A QUOTE