Homework answers / question archive / Jumpst Corporation uses the cost formula Y = $3,600 + $0,30% for the maintenance cost in Department B, where X is machine-hours
Jumpst Corporation uses the cost formula Y = $3,600 + $0,30% for the maintenance cost in Department B, where X is machine-hours. The August budget is based on 10,000 hours of planned machine time. Maintenance cost expected to be incurred during August is
The value of X is to be placed in the above equation for getting the answer.
Y = 3,600 + (0.30 × 10,000)
= 3,600 + 3,000
= 6,600
Answer: $6,600