Homework answers / question archive / Consider a project with the following cash flows: Year t = 0 t =1 t = 2 t = 3 t = 4 ??? $7,500 $12,500 $15,000 $17,500 The Payback Period of this project is 2

Consider a project with the following cash flows: Year t = 0 t =1 t = 2 t = 3 t = 4 ??? $7,500 $12,500 $15,000 $17,500 The Payback Period of this project is 2

Finance

Consider a project with the following cash flows:

Year t = 0 t =1 t = 2 t = 3 t = 4

??? $7,500 $12,500 $15,000 $17,500

The Payback Period of this project is 2.6 years. The appropriate discount rate is 13%. Find the Net Present Value of the project. 

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Computation of the cash flow at year 0:-

Initial cost = $7,500 + $12,500 + ($15,000*0.6)

= $7,500 + $12,500 + $9,000

= $29,000