Fill This Form To Receive Instant Help
Homework answers / question archive / Consider a project with the following cash flows: Year t = 0 t =1 t = 2 t = 3 t = 4 ??? $7,500 $12,500 $15,000 $17,500 The Payback Period of this project is 2
Consider a project with the following cash flows:
Year t = 0 t =1 t = 2 t = 3 t = 4
??? $7,500 $12,500 $15,000 $17,500
The Payback Period of this project is 2.6 years. The appropriate discount rate is 13%. Find the Net Present Value of the project.
Computation of the cash flow at year 0:-
Initial cost = $7,500 + $12,500 + ($15,000*0.6)
= $7,500 + $12,500 + $9,000
= $29,000