Homework answers / question archive / ?(Mutually exclusive projects and? NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash? flows: Year Project A Project B Cash Flow Cash Flow 0 ?$(95,000?) ?$(95,000?) 1 32,000 0 2 32,000 0 3 32,000 0 4 32,000 0 5 32,000 230,000 If the appropriate discount rate on these projects is 12 ?percent, which would be chosen and? why? The NPV of Project A is ?$ nothing
?(Mutually exclusive projects and? NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash? flows:
Year Project A Project B
Cash Flow Cash Flow
0 ?$(95,000?) ?$(95,000?)
1 32,000 0
2 32,000 0
3 32,000 0
4 32,000 0
5 32,000 230,000
If the appropriate discount rate on these projects is 12 ?percent, which would be chosen and? why?
The NPV of Project A is ?$
nothing
. ?(Round to the nearest? cent.)
Project B should be taken as it has higher NPV since the projects are mutually exclusive i.e. if we accept one the other gets rejected so Project B with higher NPV is better option.