Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive /  What is the difference between fixed costs and variable costs? Consider you own a pizzeria

 What is the difference between fixed costs and variable costs? Consider you own a pizzeria

Economics

 What is the difference between fixed costs and variable costs? Consider you own a pizzeria. Give examples of its Variable costs. Give examples of its fixed costs. What would the shapes of total cost curve (TC) and the variable cost (VC) be? Why?

3. Apply the shutdown principles to the following:
a. If the product price is $24 and the AVC is $16, what would you advise the firm?
b. If the product price is $24 and the ATC is $28, what would you advise the firm?
c. If the product price is $24 and AVC is $20 and the ATC is $30, what would you advise the firm?

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

2.

Fixed costs are the costs that are fixed with a manufacturing process. For example, the rent of a place, machineries, and ovens fall under this category.

Variable costs are those costs which adds up to the costs of producing per unit of a product. For example, Flour, cheese and bacon are variable costs depending on the order made by the customer.

Total cost cuve is U shaped as the total cost keeps on decreasing and reaches the minimum (economies of scale) i.e. the optimal production and from there on every additonal unit will push the total cost up.

Variable cost is almost U shaped with upward sloping due to the principle of variable proportions.

3.

According to the shutdown principles, in the short run a firm should continue to operate if price is equal to or above the average variable costs. sfsdf

i)

Since 24>16, the firm can continue to operate under these circumstances

ii)

In the long run, the price needs to be greater than the average total cost. As 24 is less than ATC in this case, hence the firm should shutdown.

iii)

In the long run, the rorice needs to be greater than the average total cost. As 24 is less than ATC (30) in this case, hence the firm should shutdown.

In the short run, the price needs to be greater than the average variable cost. As 24 is less than AVC (20) in this case, hence the firm should continue operations in the short run.

Hope this helps. Cheers!