Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / The Get-Well hospital wishes to monitor the time to admit a patient using a control chart

The Get-Well hospital wishes to monitor the time to admit a patient using a control chart

Computer Science

The Get-Well hospital wishes to monitor the time to admit a patient using a control chart. Time to admit a patient in minutes observed are shown in the table below.

Subgroup Number

X1

X2

X3

1

6.8

5

5

2

6.6

4.9

5.2

3

6.2

5.6

6

4

6.5

4.7

5.7

5

5

6.2

6.5

6

6.8

5

5

7

6.6

4.9

5.2

8

8

9

7

9

6.5

4.7

5.7

10

5.3

6.2

6.5

11

4.8

5

5

12

6.6

4.9

5.2

13

7

5.6

6

14

7

4.7

5.7

15

5.3

6.2

6.5

16

6

5

5.8

17

6.2

4.9

5.6

18

7

6.8

6

19

6.7

4.7

5.5

20

7.5

8.3

7.6

21

6

5

5.8

22

6.2

4.9

5.6

23

7

5.6

6

24

6.7

5.1

5.5

25

7.5

6.2

4.3

  1. What type of control chart should be used for this process? (10 points)
  2. Using Minitab, find the REVISED control chart: UCL, CL, and LCL for both charts. (16 points) ( include these values in the text box answer and attach the image of the control charts)
  3. Estimate the process mean (3 points) 
  4. Estimate the process Standard deviation (3 points) (show your work by including the formulas and identifying the relevant parameters)

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Related Questions