Homework answers / question archive / Problem Assignment #3 Total points: 10 Data for a project is shown below: Activity Duration (months) Precedence Budget or Plnd
Problem Assignment #3
Total points: 10
Data for a project is shown below:
Activity |
Duration (months) |
Precedence |
Budget or Plnd. Cost |
Percent Completed |
A |
3.00 |
- |
15000 |
100 |
B |
1.00 |
- |
5000 |
100 |
C |
2.00 |
A |
10000 |
90 |
D |
3.00 |
A |
21000 |
100 |
E |
2.00 |
B |
32000 |
90 |
F |
1.00 |
C, D, E |
5000 |
0 |
G |
1.00 |
E |
5500 |
0 |
The project started on June 1st. The project has a planned duration of 7 months. Table above shows percent activities completed as of end of November.
Data below are planned cost and actual cost (spent) from June to November:
Planned Actual
Month Cost Cost
June 5000 6000
July 5000 6000
Aug 5000 8000
Sept 12000 15000
Oct 28000 30000
Nov 28000 30000
#2) Status of activities of a project are given below. Based on the information, determine which activities are on time or early or behind schedule? (4 points)
Activity Budgeted Cost Actual Cost Critical Ratio
A 300 200 1.0
B 125 250 0.5