Why Choose Us?
0% AI Guarantee
Human-written only.
24/7 Support
Anytime, anywhere.
Plagiarism Free
100% Original.
Expert Tutors
Masters & PhDs.
100% Confidential
Your privacy matters.
On-Time Delivery
Never miss a deadline.
Randburg Ltd is a manufacturing company that is about to launch a new product: Product Y
Randburg Ltd is a manufacturing company that is about to launch a new product: Product Y. Details of the variable costs incurred in producing one unit of Product Y are as follows: Labour R30 per hour Materials R40 per unit Variable overheads R10 per labour hour
Additional Information Product Y is produced in batches of 25 units. The first batch of 25 units is expected to take 15 labour hours. There will be 80% learning curve that will continue until 60 batches have been produced. There after learning will stop, and the average time taken for the 60th batch will be same for the remaining batches. The total output expected is 100 batches. Required: a. Calculate the time required to produce the 60th batch of Product Y [15] b. Calculate the total variable cost of the 60th batch of Product Y [10] c. Calculate the total time take to manufacture 100 batches [5] Critically discuss the three conditions that must exist in the production process of Product Y, for the learning curve effect to be realised, use valid arguments in your answer [20]
Expert Solution
| a) | |||||||
| Time taken to produce first batch | 15 | ||||||
| Average time taken for 2 batches | 12 | Percent of first batch | 80% | (12/15) | |||
| Average time taken for 4 batches | 9.6 | Percent of average time of 2 batches | 80% | (9.6/12) | |||
| The time taken in this case follows 80% Learning Curvre | |||||||
| The Equation will be | |||||||
| Y=a(X^b) | |||||||
| Y=Average time taken per batch | |||||||
| a=Time taken to produce the first batch= | 15 | hours | |||||
| X=Cumulative bathces till learning curve is applicable= | 60 | ||||||
| b=Learning index | |||||||
| For 80% Learning Curve | |||||||
| b=Log0.8/Log2=-0.322 | |||||||
| Y=Average time =15*(60^(-0.322))= | 4.014 | hours | |||||
| Total time required for 60 batches=60*4.014 | 240.81 | hours | |||||
| If X=59 | |||||||
| Y=Average Time for 59 batches=15*(59^(-0.322))= | 4.04 | Hours | |||||
| Total Time required to produce 59 batches=59*4.04 | 238.08 | Hours | |||||
| a | TIME REQUIRED TO PRODUCE 60TH BATCH=240.81-238.08 | 2.73 | Hours | ||||
| b | Total Variable Cost of the 60th batch: | ||||||
| Direct Materials=40*25 | 1,000.00 | RM | |||||
| Direct Labor=30*2.73 | 81.86 | RM | |||||
| Variable Overhead=10*2.73= | 27.30 | RM | |||||
| TOTAL VARIABLE COST OF 60TH BATCH | 1,109.16 | RM | |||||
| c | TIME TAKEN TO MANUFACTURE 100 BATCHES | ||||||
| Time taken for first 60 batches | 240.81 | Hours | |||||
| Time taken for remaining (100-60=) 40 batches=40*2.73 | 109.20 | Hours | |||||
| TIME TAKEN TO MANUFACTURE 100 BATCHES=240.81+109.20 | 350.01 | Hours | |||||
| d | THREE CONDITIONS THAT MUST EXIST: | ||||||
| 1. Pressure or motivation to improve | |||||||
| 2.Continuity of production | |||||||
| 3.Constant improvement in production process |
Archived Solution
You have full access to this solution. To save a copy with all formatting and attachments, use the button below.
For ready-to-submit work, please order a fresh solution below.





