Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / Develop a network for this data, total project completion time and the critical path: Activity immediate Predecessor Time(days) A - 2 B - 5 C - 1 D B 10 E A,D 3 F C 6 G E,F 8

Develop a network for this data, total project completion time and the critical path: Activity immediate Predecessor Time(days) A - 2 B - 5 C - 1 D B 10 E A,D 3 F C 6 G E,F 8

Statistics

Develop a network for this data, total project completion time and the critical path:

Activity immediate Predecessor Time(days)

A - 2
B - 5
C - 1
D B 10
E A,D 3
F C 6
G E,F 8

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Please see the attached file.

Develop a network for this data, total project completion time and the critical path:

Activity                                      immediate Predecessor                Time(days)

A                                                        -                                          2
B                                                        -                                           5
C                                                        -                                          1
D                                                        B                                         10
E                                                        A,D                                      3
F                                                         C                                        6
G                                                        E,F                                       8

Activity Predecessor Time
A 1-2 - 2
B 1-3 - 5
C 1-4 - 1
D 3-2 B 10
E 2-5 A,D 3
F 4-5 C 6
G 5-8 E,F 8