Jacks Contractors received a contract to construct a mental health facility for $2,500,000

Business Aug 29, 2020

Jacks Contractors received a contract to construct a mental health facility for $2,500,000.

Construction was begun in 2005 and completed in 2006. Cost and other data are presented below:
2005 2006
Costs incurred during the year $1,500,000 $1,300,000
Remaining estimated costs to complete 1,200,000 0
Billings during the year 1,200,000 1,300,000
Cash collections during the year 1,000,000 1,500,000

Assume that Jacks uses the percentage-of-completion method for revenue recognition.

Compute the amount of gross profit recognized during 2005 and 2006.

Expert Solution

2005
The costs incurred are 1,500,000 and the total cost to complete the project are 1,500,000+1,200,000=2,700,000. Since there is a loss as the total income from the contract is 2,500,000, the gross loss of 200,000 will be recognized in 2005.

2006

The additional costs incurred result in loss of 100,000 which will be recognized in 2006

Year 2005 2006
Gross Profit (200,000) (100,000)

Archived Solution
Unlocked Solution

You have full access to this solution. To save a copy with all formatting and attachments, use the button below.

Already a member? Sign In
Important Note: This solution is from our archive and has been purchased by others. Submitting it as-is may trigger plagiarism detection. Use it for reference only.

For ready-to-submit work, please order a fresh solution below.

Or get 100% fresh solution
Get Custom Quote
Secure Payment