Homework answers / question archive / Complete all the yellow cells for the MPS record below

Complete all the yellow cells for the MPS record below

Operations Management

Complete all the yellow cells for the MPS record below. If the value is zero (0) be sure to enter a 0 in the cell. SHOW YOUR WORK!

Item: ABC

Lot Sizing Rule: FOQ = 100

Lead time: 1 week

Beginning Inventory: 80

Week 1 2 3 4 5 6 7 8 9 10 11 12
Gross Requirements 25 25 25 25 30 30 30 30 35 35 35 35
Projected On Hand (80)                        
Planned Orders (MPS)                        

Option 1

Low Cost Option