Strayer University
BUS 430
TRUE/FALSE
1)Because the preparation of annual reports is done on a repeating basis, project management techniques are not appropriate
Management May 28, 2021
Strayer University
BUS 430
TRUE/FALSE
1)Because the preparation of annual reports is done on a repeating basis, project management techniques are not appropriate.
Project management objectives revolved around on-time and budget performance.
Astatement ofwork would be developed in the "Organize" step of the project life cycle.
Project managers need to be specialists, not generalists.
In most organizations, projects cut across organizational boundaries, making it difficult to implement projects exclusively within functional departments.
In a matrix organization, functional managers may be reluctant to provide the resources and employees, and the employees assigned to projects may relegate a project to a lower priority than their daily functional job.
Strong leadership is an impediment to project management success because of the team-based nature of most projects.
Immediate predecessors are activities that must be completed immediately before an activity may start.
Withthe Activity-On-Node (AON) network, the nodes define the precedence relationships and the arcs define the work activities.
Activity times must be estimated from historical data of similar work tasks to provide realism for a project.
The critical path is the sequence of activities that takes the longest time.
To compute the critical path, we assign all nodes in the network an earliest starting time of zero.
The early start time for an activity is computed by finding the largest early finish time of all immediate predecessors.
All activities on the critical path have a zero slack time.
AGanttchartisa usefultoolfor allocating limited resources among project activities.
A slack of (-2) means the project is ahead of schedule by two time periods.
Crashing refers to the process of shortening selected activity times in order to reduce the overall project completion time.
The Critical Path Method (CPM) allows for an evaluation of uncertainty in project completion times.
Using a beta probability distribution to characterize uncertain activity times is practical because it allows managers to use judgmental estimates to identify the distribution.
When the beta probability distribution is used to characterize uncertain activity times, the distribution of the project completion time will also have a beta probability distribution.
When finding the earliest finish (EF) time for an activity with two or more predecessor activities, the largest EF among the predecessor activities is used to calculate the EF for that activity.
The slack for an activity is equal to its latest finish time minus its earliest start time.
We should not crash activities on the critical path.
MULTIPLE CHOICE
The county government has decided to redo the street you live on and plans to block the street off which causes you and your neighbor's considerable inconvenience. The project has three parallel paths defined as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 16 days, (ii) path A-D-E-H to install sidewalks with handicap capabilities that takes 22 days, and (iii) path A-F-G-H to repave the street including storm drains that takes 30 days. Which one of the following statements is true?
The expected duration of the project is 30 + 22 + 16 = 68 days.
PathA-B-C-H isthecritical path.
PathA-D-E-H has the most slack time.
PathA-F-G-H isthecritical path.
Aprojecthasthreepaths.A-B-C has a length of 25 days. A-D-C has a length of 15 days. Finally, A-E- C has a length of 20 days. Which one of the following statements is true?
A-D-C is the critical path.
A-B-C has the most slack.
The expected duration of this project is 25 days.
The expected duration of this project is 25 + 15 + 20 = 60 days.
Which of the following is not considered a project?
Writing and implementing a computer program
Introducing a new product
Production of soft drinks
Building a bridge
Which of the following is not a stage in the project life cycle?
Define
Organize
Improve
Close
In which stage in the project life cycle would critical path calculations be performed?
Define
Plan
Organize
Control
In which stage in the project life cycle would crashing likely be performed?
Define
Plan
Organize
Control
In which stage in the project life cycle would a Gantt chart be used?
Define
Plan
Organize
Control
A type of organization which "loans" resources to projects while still maintaining control over them is called
Pure project structure
Pure functional structure
Matrix structure
Product structure
A type of organization that can result in inefficiencies because of duplication of resources across the organization is called
Pure project structure
Pure functional structure
Matrix structure
Product structure
Which step in the project management process would involve determining time estimates for activities?
Project definition
Resource planning
Project scheduling
Project control
Which step in the project management process would involve developing alternative plans in anticipation of problems that might arise?
Project definition
Resource planning
Project scheduling
Project control
Which of the following is not an assumption of the critical path method?
Activities are independent of one another
Activity time estimates are stable
Activity times are characterized by a beta probability distribution
Once an activity is started it continues uninterrupted until completion
Which is incorrect regarding the critical path?
Shortest time to complete a project
Longest time to complete a project
Project path with 0 slack
Delays in activities will delay the project
Slack in an activity is computed as
ES - LS
EF - LF
LS - ES
LS - EF
Which of the following is incorrect regarding time/cost trade-offs?
The relationship between time and cost is proportional
Some activities cannot be crashed
The minimum cost can be found by crashing all activities as much as possible
Crashing priority is based on the amount of uncertainty in activity times
Which statement is true regarding activities not on the critical path?
Usually cannot be delayed
Have less slack than activities on the critical path
Can delay a project if they are highly variable
Are used to crash project completion times
Which of the following is least related to Program Evaluation and Review Technique (PERT)?
Beta distribution
Variance
Most probable time
Crashing
SHORTANSWER
Define a project. Give some non-manufacturing or non-construction examples.
Explain the stages of the project life cycle.
Explain the role of the project managers and some principles for success.
Describe how a project fits into each of the three common organizational structures.
Describe the four major steps in the project-planning process.
Define critical path and explain how it is identified once a project schedule is calculated
Explain the purpose of Gantt charts.
Explain the three time estimates used to characterize uncertainty of activity times in the Program Evaluation and Review Technique (PERT) procedure.
List at least six principal factors (contributors) to project success.
PROBLEM
The network below represents a project being analyzed by the Critical Path Method.
What activity must be on the critical path, regardless of activity durations?
What isthe duration of path A-B-E-H-J?
What is the critical path of this network?
What is the length of the critical path?
The following network shows all the major activities on the circles (nodes). Each node contains time estimates in weeks.
Complete the following table.
Activity
Time
EarliestStart
EarliestFinish
LatestStart
Latest Finish
Slack
On Critical Path?
A
B
C
D
E
F
G
H
The following network shows the activities on the circles or nodes. Time estimates are in weeks.
Complete the following table:
Activity
Time
EarliestStart
EarliestFinish
LatestStart
Latest Finish
Slack
On Critical Path?
A
B
C
D
E
F
Consider the project network and data shown below:
Activity
Slack
Normal Time
Crash Time
Normal Cost
Crash Cost
Crash Cost Per Week
A
0
7
4
$ 400
$ 750
B
1
12
9
$ 1,000
$2,200
C
0
7
6
$ 800
$1,100
D
0
6
5
$ 600
$1,000
E
0
8
6
$ 1,200
$2,200
F
9
3
2
$ 800
$1,000
G
9
3
2
$ 500
$ 650
H
0
4
3
$ 400
$ 600
I
0
6
5
$ 900
$1,300
Determine the critical path and the project completion time.
Determine the crash cost per week for all activities
Which activities need to be crashed to reduce the project's completion time by 4 weeks? How much does this cost?
Consider the project network and data shown below:
Activity
Normal Time(Months)
Crash Time(Months)
Normal Cost
Crash Cost
Crash Cost/Month
A
3
2
$100,000
$150,000
B
6
4
$200,000
$320,000
C
2
2
$ 90,000
$ 90,000
D
2
1
$180,000
$250,000
E
4
2
$225,000
$450,000
F
7
6
$ 80,000
$120,000
G
4
2
$310,000
$500,000
H
2
2
$400,000
$400,000
Determine the critical path.
If management wants the project done in one less month, which activity should they crash?
Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K.
Activity
Optimistic Time
Most Likely Time
Pessimistic Time
A
7
9
14
B
2
2
8
C
8
12
16
D
3
5
10
E
4
6
8
F
6
8
10
G
2
3
4
H
2
2
8
I
6
8
16
J
4
6
14
K
2
2
5
Determine the standard deviation of the critical path.
Determine the probability of completing the project in 38 weeks or less.
What is the probability of completing the project in 32 weeks or less?
An electrical contracting company has been awarded a government contract to install lighting fixtures on a major highway. They want to use a horizontal bar chart to plan the schedule for the contract with work to begin on January 1 and assuming four weeks per month. The company has established the following project activities, their precedence relationships, and their estimated normal times:
Activity
Immediate Predecessors
Normal Time (weeks)
a. order materials
none
4
b. clear job sites
none
6
c. excavate job sites
b
10
d. make trenches for conduit
b
6
e. install conduit
d
10
f. form and pour foundations
c, d
8
g. install wire
f
6
h. install lighting standards
g
5
i. install luminaries
h
4
j. connect to service
i
3
When does activity d begin?
When does activity f end?
The production engineering group at the Singapore plant of a computer company has been put in charge of production for a new printer model. The printer will be built via an assembly line. The plant manager must design the assembly line for the printer. He has been advised that the assembly line must be ready in four weeks for a test run. He has decided to use CPM and has identified these activities, determined their precedence relationships, and estimated normal times:
Activity
Immediate Predecessors
Normal Time (days)
a. organize layout team
none
5
b. organize modification team
none
3
c. design personnel jobs
a
2
d. set machinery in place
b
3
e. connect utilities
c, d
7
f. modify conveyor system
e
4
g. train personnel
e
3
h. finishing touches
f
5
i. run test lot
g
2
How many paths are there in the network?
What is the duration of path b-d-e-g-i in days?
What is the earliest finish (EF) time for activity “e”?
What is the slack in days for activity "d"?
What is the critical path?
What is the duration of the critical path in days?
A manufacturing company is planning to use PERT to setup a project for a new production line. For this project, they have established the following activities, precedence relationships, and time estimates in days:
Activity
Immediate Predecessors
Optimistic to
Most Likely tm
Pessimistic tp
a
none
8
10
12
b
none
6
7
9
c
b
3
3
3
d
a
10
15
20
e
d
6
7
8
f
c
9
10
11
g
d
5
7
10
h
e,f
14
15
16
What is the expected duration for activity b?
What is the variance of activity d?
How many paths are there in the network?
What is the earliest finish (EF) time for activity e?
What is the slack in days for activity c?
What is the critical path?
What is the duration of the critical path in days?
What is the standard deviation of the critical path?
What is the probability of completing the project within 50 days?
A company wants to develop a project using PERT to modify one of their products which has poor sales. They have determined the following activities, precedence relationships and time estimates in days for the project:
Activity
Immediate Predecessors
Optimistic
to
Most Likely
tm
Pessimistic
tp
a
none
4
6
7
b
a
1
2
3
c
a
5
5
5
d
b
7
9
12
e
b
2
4
8
f
c,d
6
9
10
What is the expected duration for activity a?
What is the variance for activity d?
How many paths are there in the network?
What is the earliest start (ES) time for activity e?
What is the slack in days for activity b?
What is the critical path?
What is the duration of the critical path in days?
What is the standard deviation of the critical path?
What is the probability that the project will take longer than 28 weeks to complete?
Acompanyhasa PERT project with path b-d-e-g-i that has these activity time estimates in days:
Activity
Optimistic
to
Most Likely
tm
Pessimistic
tp
b
15
17
20
d
21
22
22
e
27
30
35
g
23
27
29
i
25
31
34
What is the expected duration for activity "e"?
What is the variance for activity "b"?
What is the standard deviation of the path?
A company has used PERT for a project and wants to minimize the probability of overrunning a contract deadline of 30 weeks. Three paths of concern in the PERT network have these mean durations and variances in weeks:
Path
te
Vt
1
27
2.32
2
25
4.12
3
29
1.89
What is the Z-score for path 1?
What is the probability of path 2 overrunning the deadline?
A company has developed a project using CPM but is interested in accelerating it if possible. The project has the following activities, durations (in weeks), costs, and precedence relationships:
Immediate
Present
Accelerated
Activity
Predecessors
Duration
Cost
Duration
Cost
a
none
3
$100
2
$250
b
a
4
$ 50
3.5
$150
c
a
5
$250
4
$450
d
none
3
$100
3
---
e
d
6
$100
5
$175
f
b,c,e
7
$300
5
$600
How many paths are in the network?
What is the earliest finish (EF) time for activity f?
What is the slack in weeks for activity "c"?
What is the critical path?
What is the duration of the critical path in weeks?
What activity should be crashed first to accelerate the project?
What is the final duration of the fully crashed project?
What is the total crashing cost for the project?
A manufacturing company wants to accelerate a project it has underway for a new product in order to beat their competitors to market. They used CPM to develop the project which has the following activities, durations (in weeks), costs (in dollars), and precedence relationships:
Immediate
Present
Accelerated
Activity
Predecessors
Duration
Cost
Duration
Cost
a
none
3
3300
2
3400
b
none
5
4100
3
4500
c
a
4
3700
3
3800
d
b
5
5900
4
6000
e
c
6
6700
4
6900
f
c
4
4100
3
4150
g
d,e
6
9100
3
9700
h
f,g
5
2700
4
3000
How many paths are in the network?
What is the latest finish (LF) time for activity g?
What is the slack in weeks for activity c?
What is the critical path for this project?
What is the duration of the critical path in weeks?
What activity should be crashed first in order to accelerate the project?
What is the final project duration in weeks assuming it is crashed as far as possible?
What is total cost to crash the project as far as possible?
You are in charge of the "advertising program" for the Boston Red Sox baseball team during their spring training in Fort Myers, Florida. You have defined the advertising program as a project with the following characteristics. The goal is to fill all stadium seats during the spring training season.
Activity
A
Immediate Predecessor(s)
none
Activity Time (weeks)
1
B
A
2
C
A
3
D
A, B
4
E
C, D
3
F
D, E
2
What is the earliest completion time for this project?
What is the largest amount of slack that any activity has in this project?
If activity C is delayed three weeks, what is the revised earliest project completion time?
For the original CPM problem, what is the minimum number of activities that would have to be crashed in order to reduce the project's earliest completion time by two weeks assuming all activity crash costs per week are the same and all activities can be crashed?
You are responsible for managing an advertising and promotion project with the following activities (times are given in weeks).
Project
Activity
Immediate
Predecessor(s)
Optimistic
Time
Most Likely
Time
Pessimistic
Time
Expected
Time
Activity
Variance
A
none
2
5
14
6
4
B
none
8
11
14
11
1
C
A
5
7
9
7
0.44
D
A
6
9
12
9
1
E
B, C, D
1
3
5
3
0.44
What is the critical path and expected completion time for this project?
Which activity has the largest slack, and how large is that slack?
What is the probability that the project will be completed within 16 weeks?
If the expected time (not the most likely time) for activity B is changed to 18 weeks from 11 weeks, by how many weeks will the project's expected completion time increase?
Expert Solution
please use this google drive link to download the answer file.
Important Note:
This solution is from our archive and has been purchased by others. Submitting it as-is may trigger plagiarism detection. Use it for reference only.
For ready-to-submit work, please order a fresh solution below.