1)Activity B of a project has a budgeted cost of $50,000 and is 30% complete. The actual cost of the activity is $12,000. What is the activity difference?
value of work completed?
deviation of five weeks. What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)
delaying the entire