Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / University of Houston, Clear Lake DSCI 3331 1)Activity B of a project has a budgeted cost of $50,000 and is 30% complete

University of Houston, Clear Lake DSCI 3331 1)Activity B of a project has a budgeted cost of $50,000 and is 30% complete

Business

University of Houston, Clear Lake

DSCI 3331

1)Activity B of a project has a budgeted cost of $50,000 and is 30% complete. The actual cost of the activity is $12,000. What is the activity difference?

  1. Activity D of a project has a budgeted cost of $45,000 and is 20% complete. What is the

value of work completed?

  1. Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks. What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.)
  2. Consider a project that has an expected completion time of 60 weeks and a standard

deviation of five weeks. What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)

  1. In PERT, we assume that- the total time to complete all activities on the critical path is described by a normal distribution.

 

 

  1. PERT assumes that the total completion time of a project follows which of the following probability distributions?
  2. Reducing the overall activity time is based on which of the following steps?
  3. Slack time in a network is the- amount of time that an activity can be delayed without

delaying the entire

 

Option 1

Low Cost Option
Download this past answer in few clicks

2.83 USD

PURCHASE SOLUTION

Already member?


Option 2

Custom new solution created by our subject matter experts

GET A QUOTE