Homework answers / question archive / Problem Assignment #2 #1) An MBA program (with an emphasis in Supply Chain Management) at a Mid-western University in the US requires completion of 12 courses
Problem Assignment #2
#1) An MBA program (with an emphasis in Supply Chain Management) at a Mid-western University in the US requires completion of 12 courses. Duration of each course is one semester. Courses required (and their prerequisites) for the MBA program are as follows:
Accounting (AC) course:
AC 701 (Prereq: None)
Finance (FN) courses:
FN 735 (Prereq: AC 701)
Supply Chain Management (SC) courses:
SC 719 (Prereq: AC 701)
SC 761 (Prereq: SC 719)
SC 763 (Prereq: SC 719)
SC 768 (Prereq: SC 761 and SC 763)
Marketing (MK) courses:
MK 719 (Prereq: None)
MK 757 (Prereq: MK 719)
Information Technology (IT) courses:
IT 715 (Prereq: None)
IT 745 (Prereq: IT 715 and MK 719)
Management (MG) courses:
MG 747 (Prereq: IT 745)
MG 771 (Prereq: FN 735, SC 768, MK 757 and MG 747)
NOTE: Assume all courses are offered every semester by the university.
#2) A restaurant chain is building a new restaurant. Following are the activities that need to be completed to get the restaurant opened. In addition, data related to the activities are provided in the table.
Activity |
Preceding Activities |
Normal Time (wks) |
Crash Time (wks) |
Expediting (Crashing) cost per week ($) |
B |
- |
18 |
15 |
1,300 |
C |
- |
16 |
14 |
1,400 |
D |
B, C |
5 |
5 |
- |
E |
D |
9 |
6 |
3,000 |
F |
E |
3 |
1 |
2,750 |
The manager of the restaurant is interested in reducing (expediting) the duration of the project by 2 weeks. Specifically, which activities (and by how many weeks) should be expedited, if the restaurant chain is willing to pay crashing/expediting cost? (7 points