Problem Assignment (Project Scheduling) #1) (6 points) Following information is available about a project
Problem Assignment (Project Scheduling)
#1) (6 points)
Following information is available about a project.
|
Activity |
Activity Time (weeks) |
Immediate Predecessor(s) |
|
A |
4 |
- |
|
B |
4 |
- |
|
C |
5 |
- |
|
D |
4 |
- |
|
E |
6 |
A |
|
F |
2 |
B,C,D |
|
G |
4 |
E.F |
|
H |
6 |
F |
|
I |
1 |
G,H |
Compute slack for noncritical activities for the project and enter them in the table below.
NOTE: Some rows in table below may be blank.
|
Activity |
Slack |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
#2) (6 points) Activity durations (in weeks) for a project are given below:
|
|
|
|
|
|
|
|
|
Activity |
Precedence |
Optimistic time |
Most likely time |
Pessimistic time |
Expected time |
Variance |
|
A |
- |
6 |
7 |
14 |
8.00 |
1.78 |
|
B |
- |
8 |
10 |
12 |
10.00 |
0.44 |
|
C |
- |
2 |
3 |
4 |
3.00 |
0.11 |
|
D |
A |
6 |
7 |
8 |
7.00 |
0.11 |
|
E |
B, C |
5 |
5.5 |
9 |
6.00 |
0.44 |
|
F |
B, C |
5 |
7 |
9 |
7.00 |
0.44 |
|
G |
D, E |
4 |
6 |
8 |
6.00 |
0.44 |
|
H |
F |
2.5 |
3 |
3.5 |
3.00 |
0.03 |
What is the probability that the project will finish 1 week early? Perform the necessary calculations and complete entries in the table below.
NOTE: Some rows in table below may be blank.
|
Path |
Probability finishing the project 1 week early |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Joint probability of completing the project 1 week early = _________
#3) (6 points)
Project description: You are hired by the SCM Faculty Coordinator to move old offices of four SCM faculty/staff from the 3rd floor (Hyland Hall) to new offices on the 4th floor (Hyland Hall).
- Items include books, computers, printers and other miscellaneous items. Furniture such as desks, cabinets and bookshelves are not to be moved.
- Unlimited boxes are available.
- Unpacking boxes is not part of the project.
- Offices on the 4th floor are move-in ready.
|
Office |
Estimated number of boxes |
|
#1 |
10 |
|
#2 |
10 |
|
#3 |
5 |
|
#4 |
5 |
Tasks and estimated task times are as follows:
Packing and labeling boxes - 6 minutes per box
Loading boxes into dolly - 1 minute per box
Moving loaded dolly (1 trip) from 3rd floor to 4th floor - 20 minutes.
Unloading boxes into offices - 1 minute per box
Moving empty dolly (1 trip) from 4th floor to 3rd floor - 10 minutes
Cleaning all old offices – total of 60 minutes
Strategy
- Hyland Hall opens at 5:30 am and closes at 5:30 pm.
- Work hours: Starts at 6:00 am;
- One dolly (capacity 10 boxes per dolly) is available.
- Dolly is “parked” on 3rd floor. Dolly needs to be returned to 3rd floor after all offices are handed over.
- Person #1 – Work package #1: Pack and label boxes in old office. Person works on one office until it is completed.
- Person #2 – Work package #2 (in sequence): Move boxes from old office to new office (i.e. Load boxes on dolly, Move dolly to new office and Unload boxes in new office, Move dolly back to 3rd floor). Person works on one office until it is completed. NOTE that Person #2 cannot start loading dolly until all boxes for an office is packed and labeled.
- Person #1 – Work package #3: Clean all old offices (at the end of the day i.e. after packing and labeling of boxes in all offices are completed).
COMPLETE TABLES BELOW.
Person #1 – Work Sequence (Office #): 1, 2, 3, 4
Work package #1: Pack and label boxes in old office
Person #1 Schedule:
|
Office |
Work package #1 Start time |
Work package #1 Finish time |
|
#1 |
|
|
|
#2 |
|
|
|
#3 |
|
|
|
#4 |
|
|
Person #2 – Work Sequence (Office #): 1, 2, 3, 4, 5, 6
Work package #2 (in sequence): Load boxes on dolly, Move dolly to new office, Unload boxes in new office and Move dolly back to 3rd floor.
NOTE: Person #2 cannot start loading dolly until all boxes in an office is packed and labeled.
Person #2 Schedule:
|
Office |
Loading-Moving- Unloading Start time |
Loading-Moving-Unloading Finish time |
Dolly return to 3rd floor |
|
#1 |
|
|
|
|
#2 |
|
|
|
|
#3 |
|
|
|
|
#4 |
|
|
|
Person #1 – Work package #3: Clean all old offices at the end of the day.
Person #1 Schedule (Work package #3)
|
Work package #3 |
Work package #3 Start time |
Work package # Finish time |
|
Clean all offices |
|
|
Expert Solution
Please download the answer using this link
https://drive.google.com/file/d/16qbpyx_qPhJ821Oz-6Ojx70gDGo2BzTz/view?usp=sharing
Archived Solution
You have full access to this solution. To save a copy with all formatting and attachments, use the button below.
For ready-to-submit work, please order a fresh solution below.