Homework answers / question archive / The amount of delay within a task that will not delay the overall project is known as a     Estimated Effort

The amount of delay within a task that will not delay the overall project is known as a     Estimated Effort

Business

The amount of delay within a task that will not delay the overall project is known as a

   

Estimated Effort.

   

Opportunity Cost.

   

Total Slack.

   

Both Total Slack and Opportunity Cost are correct.