If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network

Business

If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a

   

Critical path.

   

Parallel path.

   

Dangler path.

   

Confused path.

   

Multiple start path.