If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a
Critical path. |
||
Parallel path. |
||
Dangler path. |
||
Confused path. |
||
Multiple start path. |