The project scope statement indicates that the client is responsible for training the people who will be using the equipment and that the project team will train the client's trainers

Business

The project scope statement indicates that the client is responsible for training the people who will be using the equipment and that the project team will train the client's trainers. This is an example of

   

Technical requirements.

   

Limits and exclusions.

   

Deliverables.

   

Milestones.

   

Project objectives.