Homework answers / question archive / The direct cost for completing an activity in the shortest time it can realistically be completed in is called its ________ cost

The direct cost for completing an activity in the shortest time it can realistically be completed in is called its ________ cost

Business

The direct cost for completing an activity in the shortest time it can realistically be completed in is called its ________ cost.

   

Accelerated

   

Reserve

   

Expedited

   

Crash

   

Normal