Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / A project manager is using the payback method to make the final decision on which project to undertake

A project manager is using the payback method to make the final decision on which project to undertake

Finance

A project manager is using the payback method to make the final decision on which project to undertake. The company has a 20% required rate of return and expects a 3% rate of inflation for the following five years. What is the discount factor for Year 3? O 0.66 0.81 O 0.44 0.54

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

Ans) 0.54

Here required rate of return = 20%

Expected rate of inflation = 3%

Thus discount rate to be used = 20% + 3% =23%

Thus Discount factor for 3rd year = 1/(1+r)^3

= 1/(1+23%)^3

= 1/(1.23)^3

= 0.54