Fill This Form To Receive Instant Help

Help in Homework
trustpilot ratings
google ratings


Homework answers / question archive / Compute the NPV for Project M if the appropriate cost of capital is 8 percent

Compute the NPV for Project M if the appropriate cost of capital is 8 percent

Finance

Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project M Time: Cash flow: 0 1 -$1,300 $410 2 $540 3 $580 4 $660 5 $160 NPV Should the project be accepted or rejected? O accepted O rejected

pur-new-sol

Purchase A New Answer

Custom new solution created by our subject matter experts

GET A QUOTE

Answer Preview

a. NPV     597.03 (Approx.)  
       
Working Notes:      
       
Notes: NPV is the net present value of cash flows during the life of project which includes cash outflows and cash inflows.
 
       
  A B C = A x B
Time Cash flow PVF @ 8% Present Value
0 -1300 1 -1300
1 410 0.925926 379.62966
2 540 0.857339 462.96306
3 580 0.793832 460.42256
4 660 0.73503 485.1198
5 160 0.680583 108.89328
    NPV 597.02836
       
       

Notes: PVF is calculated @ r% = 1/(1+r%)^n    for given case used is (1/(1.08)^n) where n is the period for which PVF is calculated.

b.      
  Accepted    
       
Working Notes:      
       
  Project M Should Be accepted as its NPV is positive i.e. 597.03 means it is able to generate more than required cost of capital of 8% , hence the project should be accepted.