S agreed to sell orange to B, and the cargo was supposed to be carried from Spain to Turkey

Economics Dec 11, 2020

S agreed to sell orange to B, and the cargo was supposed to be carried from Spain to Turkey. The vessel SAMARA nominated for the voyage, and the ships name was inserted to the bill of lading. However, the ship SHARA was made available at the loading port by the seller. There was a delay, and huge rise in import duty. The buyer refused to make a payment on the basis that the name of the vessel was wrong ,and term is a contractual description of the goods. Would the buyer reject the payment due to a wrong ship name?

a. Yes

b. No

c. Ship name is not the part of a contractual description.

Expert Solution

C) Ship name is not the part of a contractual description

In this case because there was a delay and huge rise in import duty .hence buyer refuse to make payment.he said reason behind refusal is that of the name of the ship is wrong.but ship name is not part of a contractual description.

Archived Solution
Unlocked Solution

You have full access to this solution. To save a copy with all formatting and attachments, use the button below.

Already a member? Sign In
Important Note: This solution is from our archive and has been purchased by others. Submitting it as-is may trigger plagiarism detection. Use it for reference only.

For ready-to-submit work, please order a fresh solution below.

Or get 100% fresh solution
Get Custom Quote
Secure Payment