ASSIGNMENT 3 STAT 2112 The product development group at IEK Group Corporation has been working on a new computer software product that has the potential to capture a large market share
ASSIGNMENT 3 STAT 2112
The product development group at IEK Group Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources, IEK Group’s management learned that a competitor is working to introduce a similar product. As a result, IEK’s top
management increased its pressure on the product development group. The group’s leader turned to PERT/CPM as an aid to scheduling the activities remaining before the new product can be brought to the market. The project network is as follows:
The activity time estimates (in weeks) are as follows:
- Develop an activity schedule for this project and identify the critical path activities.
- What is the probability that the project will be completed so that IEK Group Corporation may introduce the new product within 25 weeks? Within 30 weeks?