Splish manufactures 3-ring binders targeted at the high school market
Splish manufactures 3-ring binders targeted at the high school market. Orders for 53,000 binders were received during July, with deliveries scheduled evenly throughout the month of August. Binders are produced simultaneously in 7 manufacturing cells. Time available for production in each cell is 7.5 hours per day for 22 days during July Calculate the takt time. (Round answer to 2 decimal places, e.g. 15.21.) Takt time minutes per binder LINK TO TEXT At the end of the first hour of a day's production, one cell had completed 40 good binders, including 5 binders that were reworked. 1. Calculate the day-by-the-hour results and the variance. (Round answers to o decimal places, e.g. 1,521. Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).) Binders demanded per hour binders per hour Variance binders 2. Calculate the first time through (FTT) rate. (Round answer to 2 decimal places, e.g. 15.21.) FTT rate
Expert Solution
1.
Net time available=7×7.5 hours×22days ×60 minutes=69,300
Takt time = Net time available/ Customer demand
Takt time =69,300/53,000 =1.31 minutes per binder
2. Binds demand per hour =1cell×1 hour×60 minutes /1.31
=60/1.31
=45.8 or 46 bindera per hour
Variance= 40-46=(6) binders
3. FTT rate = (units produced - Defective units) l Units produced
FTT rate =(40-5)/40
FTT rate =87.5%